Water Board Rejects Two Change Orders, OKs One

The West Bridgewater Water Commission rejected two contractor change orders and approved a third tied to its Norman Street treatment plant project.

Email Text Facebook X

Water · Meeting of October 19, 2026

WEST BRIDGEWATER — The West Bridgewater Water Commission rejected two contractor change orders and approved a third tied to its Norman Street treatment plant project. Owner's project manager James Floyd told the board the project's contingency balance stood at $689,500 even after the approved change, calling the extra costs "not zero" but far below budget reserves. Commissioners voted down a $1,675 claim for extra concrete work and a foundation-modification claim, both from contractor Waterline, saying the costs should not fall on the water department.

The board also authorized a $28,149 payment to Eversource for gas-trench work and delegated signing authority to Commissioner Phil. At the Manly PFAS treatment plant, the state Department of Environmental Protection is withholding the final 5 percent of payment, calling outstanding punch-list items warranty work rather than unfinished construction.

In the full story:

  • Minutes, Warrants and Routine Business
  • Norman Street Treatment Plant Change Orders
  • Manly PFAS Treatment Plant Warranty Dispute and Media Performance
  • Emerging Contaminants Grant Reimbursement
  • Eversource Gas Service Agreement
  • Water Superintendent Updates and Personnel
  • Wayne Park's Vacation Carryover and Adjournment
  • Who Was There
  • Organizations And Documents Referenced
  • The complete report: 2,836 words

Source: the Water meeting of October 19, 2026, reported from the official video recording and transcript.

Checked against the record: before publication this article was automatically compared with the meeting transcript.

Members read the rest of this story and every Plymouth County meeting we cover, in full.

Become a member

A 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms

Share this story

Email Text Facebook X

Know someone in Plymouth County who follows town government? Share Townbrief Plymouth County: they can sign up free.

Share this story

Email Text Facebook X

Anyone can open a shared story. Members' stories show the free part and a sign-up line to people who are not members.